Angry Handover

Quote:
Originally Posted by wayneis View Post
The Building owner is given the opportunity to inspect the building before hand over. You would expect that the building owner would take an interest in the condition of your apartment before you take possession how ever the reality is some what different.

Nakheel should not be letting this still happen, after many many months of hand overs along with 1,000's of apartments in International City the process of snagging known faults and quality control should be down to a fine art. To read posts where this is still occurring is disappointing.

It would assist other owners if you are able to post photos and faults that you are finding in the snagging process. If we get several comments I will start another thread.
Wayneis

What you have said is correct, the developer (Nakheel) should have given the keys to the Building owner on 9th Sept and there should have checked it out.
But what happened is Nakheel gave the keys HOURS before we got ours. So again Its Nakheel messing about with dates !!!!!!