HI ALL,
I HAVE RECEIVED THIS EMAIL FROM ALATTAR RECENTLY
Toronto Tower (International City Projects) Update
The compliance certificate/permission to build for Vancouver was recently awarded by Nakheel. We expect the same to happen for Toronto and Global Point in the next month. Preparations are well underway to break ground, and we are submitting re-design requirements to the Master Developer addressing their enhancements on utilities and services. The integrated master plan for Phase II and III paved the way for better educational, religious and recreational facilities and in a letter issued 31st of July 2007 has also seen utilities and services developments from a centralized gas system, to better TSE (Treated Sewerage System), which makes the Integrated International City Phase II and III a definitely better product. The integration information is available in our new website:
Al Attar Properties.
Attached herewith are infrastructure pictures taken from Phase II and III sites. We are always in touch with Canadian Consultant, and diligently requiring a progress report from them. These project management progress reports will be further cascaded via direct mail and email shots. The first Customer Relationship Management Cascade (CRM) has been sent to all International City Project owners and will be done by batches. Please confirm if you receive yours. In addition, please anticipate upcoming cascades that will entail all International City Projects.
At the onset, we have project forecasted the construction of the basement from this date to be 7-8 months. We anticipate completion date to be Mid-2009.
At the crux of the issues within our organization is our customer relationship management initiatives. We have initially implemented stop-gap solutions, and working on incorporating within our systems, process and people, sustained, long-term ones.