Hello Folks,

I'm new to the community and since i live in a rented apartment in intl city, i thot i cud help u guys out.

I've recently purchased an apartment myself in france in building q5.

Upon the purchase i was informed by my agent that the nakheel handover date is December 12th (i also haf the letter stating that).

however, my agent was nice and kind enuff to inform me, that even tho that might be the date they've issued, realisticly the apartment will be handed over in Jan.

The DEWA requirements for the buildings have been met(according to what i was told by my agent.) Cluster P's apartments' have their lights on too at nights because i guess they're doing the snagging work and finishing up on that. (usually when the apartment lights are on it means the apartments are nearly done and extremely close to handover. This is what i've experienced, having lived in intl city for nearly 6 months now).

Cluster Q had two buildings which required some work on the outside being finished up and they are now nearly done. So things are looking good. Unfortunately, i don't know anything abt cluster R (i think its r, at least) except that its the cluster thats yellow and red (instead of grey and cream).

The inner road lights of france are also starting to turn on.

If you have any more questions... feel free to ask..