Update from the developer
Hi - for any buying on Sierra this is an update that I have received directly from the developer today
Dear ALISON
Greetings,
So SORRY for the late reply ,i had extended my visit to SHARM due to long list of topics i had to solve ,please accept my apologies.
now concerning zone 3 where Building 40 is located its improving -but building 40 is still not ready -we discussed it with my site engineers and they promised will be ready by end March.i know you might be upset but please don't -the site is looking more than great and electricity is now underway( sierra will be on the grid next sunday) they are working already(checking cables and power house and transformers) .
engineers from the suppliers and vendors and the electrical department are in the site as we speak -but they promise to finish next sunday.
water tank is filled and pumps are there(only the fire pumps still on the way cause it was shipped from Europe like 10 days ago and i think it need another week in customs then will be transported to the site and will be installed then.(it took 4 month to be delivered from the manufacturer) that why it took so long. i only mention it just now cause we got the shipping info.
landscaping is in progress and i can say now by the time your unit will be ready Zone 2-3-4-5 will be almost ready so the picture will be much different than now inside the Zones.
please contact me again in 2 weeks to check the progress and update you with the situation in the site.
BEST REGARDS.
TAREK SOKKAR
|